Registration of gas documents: procedure for concluding a contract for gasification

List of documents for concluding an agreement for the supply of natural gas with OOO Dnepropetrovskgaz Sbyt / Dneprogaz

What is a collective application?

Not everything is always as simple as it seems. If the nearest gas pipeline is not capable of accepting new subscribers in terms of power or is located more than 200 meters from the house, the cost of bypassing and a single connection will be simply sky-high.

Registration of gas documents: procedure for concluding a contract for gasification

When submitting a collective application, the costs of technological connection are distributed among subscribers, thereby the total amount becomes much less

Especially often such a problem is faced by remote settlements in which the general gasification program does not yet work at all.

In this case, when several facilities wish to conduct gas for themselves, the request for the development of specifications and the connection agreement can be in the form of a collective application for technological gas connection. It is enough just to unite in a non-profit partnership. At the same time, one representative can act on behalf of all residents.

However, the peculiarities of gasification of a particular subject of the Russian Federation and the package of necessary documents should be agreed with the resource supply organization, again, it may vary taking into account the characteristics of the area and the remoteness of the gas pipeline.

Basic rules for gasification in an apartment

In the process of drawing up individual technical conditions, the purposes of gas use by the owner of the apartment are taken into account, including the number of gas appliances installed. It is on the basis of this information that a list of requirements is compiled.

Employees of GorGaz do not always include mandatory rules for the installation of gas equipment in the technical specifications, therefore, due to their failure to comply, an employee of the Ministry of Emergency Situations will be forced to postpone the date of gas connection

You can get acquainted with the established rules for the installation of gas equipment inside the apartment in the document SP 42-101-2003 “General provisions for the design and construction of gas distribution systems from metal and polyethylene pipes”.

According to the document, there are a number of minimum requirements established for all gas consumers:

  • painting the gas pipe white;
  • ensuring the sealing of the chimney installation site with cement mortar;
  • installing a grate on a ventilation duct;
  • installation of a kitchen door with a 3 cm undercut from the floor, and installation of a decorative grille at a distance of 10 cm from the floor;
  • installation of electrical outlets next to the boiler, and an alarm located in the area of ​​\u200b\u200bthe gas meter;
  • purchase of a voltage stabilizer for the boiler;
  • obligatory purchase of a gas stove until the inspection is carried out by the inspector;
  • connection of gas-using equipment with stainless steel hoses, no more than 1.5 m long;
  • purchase of a gas stove equipped with a “gas-control” system;
  • availability of all necessary technical documentation for the gas equipment used.

Non-compliance of gas-using equipment with elementary technical requirements is already the basis for refusal to conclude an agreement by the gas supply service.

In order not to slow down the process of connecting gas in the apartment, it is important to fulfill all the established requirements in advance, and only after that call a specialist for an inspection. For all residents of an apartment building, the installation of indoor gas monitoring sensors is mandatory from June 6, 2019

For all residents of an apartment building, the installation of indoor gas monitoring sensors is mandatory from June 6, 2019

Another prerequisite is the installation in the kitchen of a residential building of "easy" glass, while in an apartment building you will also need to install gas sensors.

Of course, such devices will require additional costs, but this will ensure safety not only for the owner of the apartment, but also for the residents of the entire apartment building.

The process of connecting the cottage to the highway step by step

Technical conditions as such are just a piece of paper with requirements and capabilities.In addition to them, among the documents for connecting the main gas to a private house, there are various plans, projects, statements, acts and contracts. The problem is that without all this paperwork it is impossible for its owner to gasify the cottage by definition. These are the norms in our country.

Registration of gas documents: procedure for concluding a contract for gasification
The process of connecting a house to a gas pipeline in Russia is strictly regulated by laws, this is done in order to limit monopolists and reduce prices for gasification of private households

The complete “ceremony” with connecting the cottage to the main gas is as follows:

  1. Estimation of gas fuel consumption volumes.
  2. Applying for TU.
  3. Receipt of specifications.
  4. Designing a gas network from the highway to the house and inside the latter.
  5. Conclusion of a contract for connection.
  6. Installation of input outside and gas equipment inside the building.
  7. Checking the readiness of all this to work.
  8. Drawing up an act of connection.
  9. Conclusion of a service contract.

Plus, it is necessary to sign more acts of delimitation of the operational responsibility of both parties and property.

The section of the gas pipe from the main to the fence of the infield belongs to the gas supply organization, and everything further is already the property of the owner of the cottage. At the same time, the gas supplier (or a subsidiary authorized by him) is obliged to maintain all gas equipment and monitor its serviceability.

The process of connecting a country house to a nearby highway includes a number of standard steps:

You will find information on how to insert into a gas main pipe in the article recommended by us for review.

Control devices

And what equipment do you think is more effective for use in gas fire extinguishing installations?

Storing electronic information in a credit institution requires responsibility, so it is necessary to select reliable fault-tolerant equipment for AUGPT.

One of the options for automatic fire extinguishing is given below.Registration of gas documents: procedure for concluding a contract for gasification

  1. Security and fire control panel S2000M. This is the control center. Here, information is collected, the outputs of different devices are combined, cross-links are created between several sections of alarm loops, and access rights to control functions are differentiated for different users. RS-485 interface, information transfer according to a given protocol.
  2. Display unit S2000-PT. Manages fire automatics, displays the status of various AUGPT equipment, notifications from other devices. The following states are possible:

fire;
ASPT blocking;
launch of ASPT;
Attention;
malfunction;
automatic on/off.

  1. Reception and control device S2000-ASPT. Manages sirens, as well as fire extinguishers. Monitoring the health of starting mechanisms for a short circuit or open circuit, setting the delay in the release of OB separately for each of the start modes, monitoring the state of the serviceability circuit, the output control circuit, the door status sensor circuit and manual start, fire alarm loops.
  2. Block signal-starting S2000-SP1. Relay expander - controls sirens, lamps, electromagnetic locks, other elements, interacts with other devices, sends alarm signals to the monitoring console.
  3. Smoke optical-electronic detector IP212-58. Ultra-sensitive smoke detector - reacts to the appearance of smoke in the room.The developed design allows to reduce the dustiness of the chamber.
  4. Electrocontact element of remote control EDU 513-3M. It is used for manual start of fire automatic equipment. In stationary mode, displays a blinking LED with a frequency of 4 seconds. Works in conjunction with the control panel.
Read also:  Why the gas burner is noisy: analysis of the reasons + valuable recommendations for fixing the problem

For the electrical supply of devices, we use an uninterruptible power supply "RIP-24" version 02P with batteries with a capacity of 7 Ah.Registration of gas documents: procedure for concluding a contract for gasification

Powered devices operate 23 hours in standby mode and 3 hours in "Fire" mode.

Here is the data on the energy consumption of the equipment used.

Source of power electrical equipment Consumption in stationary mode (mA) Consumption in "Fire" mode (mA)
RIP S2000M 35 35
S2000-PT 20 130
S2000-SP1 15 150

Why gasify housing

Today, natural gas is the most convenient and, importantly, profitable type of fuel. Sooner or later, every owner of a private house will want to gasify his possessions. Of course, there is an alternative - electricity.

However, its cost is too high and it is very expensive to heat large areas in winter in this way. Plus, you will always depend on weather conditions - any hurricane can provoke a rupture of cables and then you will have to stay for a while without food, hot water and heating. But it is much more difficult to spoil the gas line

Of course, there is an alternative - electricity. However, its cost is too high and it is very expensive to heat large areas in winter in this way.Plus, you will always depend on weather conditions - any hurricane can provoke a rupture of cables and then you will have to stay for a while without food, hot water and heating. But to spoil the gas line is much more difficult.

Registration of gas documents: procedure for concluding a contract for gasification

Photo of natural gas

There is, of course, another "grandmother's" way to heat a home - a stove or a fireplace. But ash, coal, firewood, all this will lead to excess dirt. It will take a lot of time and labor to fire up the stove, so this option is best left as an alternative in case of an apocalypse. So, whatever one may say, but blue fuel today occupies a leading position.

The process of connecting the cottage to the highway step by step

The process of connecting a house to a common gas main consists of the following steps:

  1. sending an executive GRO application for the provision of technical specifications for connecting a house;
  2. issuance of specifications for gas supply in a private house;
  3. sending the executive organization an application for drawing up an agreement on connecting the facility to the gas main in case of a positive decision of the previous issue;
  4. drawing up a connection agreement;
  5. performance of work on connecting the facility to the gas network in accordance with the technical conditions and the concluded contract;
  6. obtaining permission from the relevant services in a legislative manner to put the gas supply line into operation after the installation of the equipment;
  7. drawing up acts: on connecting the house, delimitation of property belonging to the parties and responsibility for its operation.

Connection Features

Registration of gas documents: procedure for concluding a contract for gasification

  1. On the specified day, pipes will be brought and laid along the laying lines.
  2. After welding, the gas valve is opened and a test run is made.
  3. It is required to collect all the executive and technical documentation so that the object is accepted by the customer, the contractor and the representative of the gas service.
  4. Then the meter is sealed and a gas supply agreement is signed.
  5. The owner must undergo a safety briefing, and then signs in a special journal.

The organization that concluded the contract is responsible for the launch of the gas pipeline. The warranty period for boilers or other equipment usually ranges from one to three years.

Watch the video in which the user explains in detail all the steps in the gasification of a private house:

Installation of a gas pipeline in a private house

The connection fee obliges the contractor to bring the gas distribution network to the connection point and prepare the facility for gas launch no later than the terms established by the contract. Wiring of communications on the site and inside the applicant's house is paid separately. If these works are carried out by specialists of the gas distribution organization, then their cost will be calculated at tariff rates. To save time for work within the boundaries of the site and inside the capital structure, third-party companies can be involved. In this case, payment is charged at market prices.

Registration of gas documents: procedure for concluding a contract for gasification

Installation of the meter when entering gas into the house from the outside

If a gas distribution network is laid to the border of the site, installation work to conduct gas to a private house for citizens of the first category must begin no later than 9 months after payment for technological connection. The connection of the house to the gas pipeline must be completed within 10 days from the start of work.

The final stage of installation work is the installation of a meter, the connection of gas appliances, checking the system for possible leaks, checking ventilation and control start-up of gas. These works can only be carried out by GDO employees. After that, an act of readiness is signed, the owner of the house receives a technical supervision receipt, and the documents are again sent to the gas distribution organization. Within three weeks, Gorgas workers should come and seal the gas meter. Then a gas supply agreement is concluded with the consumer and the capital structure is included in the gas supply system. These relations are regulated by Government Decree No. 549.

Registration of gas documents: procedure for concluding a contract for gasification

Insertion into the central gas pipeline for connecting a residential building

Third stage: purchase of equipment necessary for gas connection

If you decide to purchase on your own, after the purchase, inform the gas workers that all the materials are available. As an option: copy all the papers from the purchased materials and hand them over to the responsible persons.

Gas workers may require a certificate from the fire department confirming the safety of work in your home / site. A package of documents for the gasification of a private house, as a whole, has been prepared. Get permission to cut.

After that, the specialists will carry out work on the installation of the above-ground and underground parts of the gas pipeline to the facade of a private building. The constructed system will be examined by a specialist growing up. technical supervision. Pay for the work carried out by a specialist. Subject to all current regulations, you will be issued a technical supervision document.

What are the technical conditions for gas

Obtaining technical conditions in an organization engaged in gas supply is the first stage in the gas supply of an individual residential building, all further work on the installation of a gas pipeline is carried out on the basis of this document. Specifications for connection to gas supply networks are an internal document of the gas supply organization and must contain the following information:

  1. address data of the object of connection to the gas pipeline;
  2. the largest volume of gas supply in cubic meters per hour;
  3. placement of the nearest point of entry into the highway;
  4. material and dimensional parameters of the gas pipeline being laid (pipeline diameter);
  5. a list of additional engineering works for the safe supply of gas through the main gas pipelines to the dwelling;
  6. on the obligation of the applicant to equip the individual highway with metering devices;
  7. a list of regulatory documents required to be observed during installation work;
  8. period of validity of technical conditions for gasification. This indicator has different values ​​depending on the volume of fuel supplied, the location and physical parameters of the highway (urban or rural areas, length) and ranges from 2 to 5 years.
Read also:  Gas heating in a private house: general principles of the device and many useful tips

The technical conditions for connecting to gas supply networks may include other information, the amount of documentation depends on the area and can be from one to three sheets.

Registration of gas documents: procedure for concluding a contract for gasification

Fig. 2 Specification for gas supply in a private house - appearance

Payment for connecting gas to a private house

After completing all legal formalities, the contractor sends an application to the executive body for tariff regulation to establish the cost of technological connection. In this case, it is necessary to notify the customer no later than 5 days from the date of sending the application. The application is accompanied by a connection agreement, a positive expert opinion of cost estimates and design documents, cost estimates indicating the cost of each type of work.

Having studied all the documentation, the executive authority within 22 days, excluding days off, approves the amount of payment for each type of work separately. If the applicant refuses to connect the household to the gas pipeline after the conclusion of the agreement and the examination, the owner of the household will compensate the contractor for all confirmed expenses.

Gas fire extinguishing

These installations use gas or gaseous reagents, which, when entering into a chemical reaction with heated air, prevent the further combustion process.

They are divided into the following ways of influencing the source of ignition.

  1. Inhibitory - gaseous reagents block the way for a further chemical reaction of combustion. It can be sulfur hexafluoride or one of these types of freons: 318C (C4F8), 227EA (C3F7H), 23, 125 (C2F5H), FK-5-1-12 (CF3CF2C(O)CF(CF3)2), carbon dioxide (CO2).
  2. Deoxidizing - non-flammable inert gas displaces oxygen from the room. These are, for example, carbon dioxide, a mixture of inergen, nitrogen, argon. Devices of this type fill the entire area of ​​\u200b\u200bthe burning room with a substance to extinguish the flame.To increase their efficiency, it is necessary to have an access control system (ACMS) that shuts off ventilation, closes doors, windows to limit air access to the fire source as much as possible.

The composition of an average fire extinguishing installation installed in rooms of different fire hazard categories includes these components:

One or more gas cylinders, which are equipped with an electric valve or a squib.

Piping from cylinders with spray tips.

Registration of gas documents: procedure for concluding a contract for gasification

  • Control device, start-up control, which activates the installation on a fire alarm signal.
  • Communication channels for information transfer (cables).
  • Devices for collecting / processing information (for example, a personal computer).
  • Fire alarms - sound sirens, speech devices, light detectors (plates).
  • Smoke removal system.

Gas extinguishing devices are significantly more expensive than their brothers - foam, water and powder fire extinguishing devices.

They are also more efficient. Therefore, this equipment is widely used in many industries, everyday life and is used to eliminate fire in:

  • production;
  • storehouses of material assets;
  • museums;
  • archives;
  • construction sites;
  • rooms with expensive electronics;
  • other socially significant objects.

They are successfully used in large buildings, rooms with a complex layout due to the high speed of distribution of the fire extinguishing agent (S).

AUGPT can operate in three launch modes:

  1. remote - start from a manual call point, usually located at the guard post or at the front door;
  2. local - activated from the start button on the cylinder with OM or from the launch device on the isothermal tank with liquid carbon dioxide;
  3. automatic - activated by a signal from automatic fire detectors.

Registration of gas documents: procedure for concluding a contract for gasification

The main advantages of gas fire extinguishing are the following qualities.

  • Do not emit pesticides in the process of work, do not pollute the environment.
  • They quickly detect fires, fill the room with gas in 10-30 seconds.
  • No damage to material assets when extinguishing a fire.
  • Large application temperature range: from -40 ºС to +50 ºС.
  • The room can be returned to a stationary state a few hours after natural ventilation.

The disadvantages of AUGPT can be called these factors.

  • Relatively costly to install and operate.
  • Do not extinguish substances that burn without oxygen.
  • Cannot be used outdoors.
  • A complete evacuation of the personnel building is required prior to commencement of work.

Re-registration of an apartment - step by step instructions

  1. Privatization. The process of re-registration of state property to a citizen. During it, a person becomes the full owner of the property, and the municipality loses the rights to the property.
  2. Donation form. This operation is carried out during the life of the owner of the apartment. You can donate the entire apartment (re-register it) or its share.
  3. Inheritance. Such re-registration of the apartment after the death of the owner takes place. The most unpleasant process for the heirs. Especially if the owner did not leave a will during his lifetime.
  4. Purchase / sale. Purchase and sale transactions are the most common. You can sell your property.The buyer after the transaction will become the full owner of the property. And then you will need to re-register the apartment for a new citizen.
  5. Rent. An annuity agreement is often concluded with elderly lonely people. But at the same time, direct re-registration will occur after the death of the owner of the apartment.

In practice, such situations rarely occur. Therefore, a donation is the most reliable re-registration. No one obliges the owner of the apartment to donate all the property. He has the right to donate only a share. This nuance must be written in the donation agreement.

Changed the rules for connecting gas to a private house

On February 9, numerous amendments that were made to the rules for connecting residential buildings to the centralized gas supply system come into force.

Let us briefly consider what the main changes are and how they will affect citizens who own private houses.

1. The procedure for calculating tariffs for technological connection to a gas pipe is being specified.

They should be differentiated depending on the list of gas connection works, the diameter and material of the gas pipeline pipes and the technical characteristics of the general gas supply system.

Regional tariff services are required to approve tariff rates for gas connection, broken down by individual categories of consumers.

The fee for connecting to the gas pipeline for citizens should be set in the range of 20 to 50 thousand rubles, and this amount now includes VAT. This will reduce the total cost of connecting to gas for individuals.

However, all expenses for supplying gas networks to a citizen's land plot are now paid separately, in excess of the established 50,000 rubles.

2.The rules for connecting to gas distribution networks distinguish three categories of consumers, depending on which they will differ somewhat.

The first category - consuming up to 20 cubic meters of gas per hour, with a distance to the point of connection to the gas pipeline up to 200 m.

Read also:  Do-it-yourself gas convector: installation steps for factory-made appliances + homemade assembly

The second category - consuming no more than 500 cubic meters. m of gas, the distance to the connection point is no more than 500 m (in rural areas), 300 m (in urban areas) on the territory of one settlement.

And the third category differs from the second only in that for connection it is necessary to cover the territory of two or more settlements.

3. The procedure for connecting the house to gas will include the following steps:

- sending a request by a citizen to provide technical conditions for connecting to the network (including via the Internet with the ability to track the progress of the application). The request can now include a request for a preliminary calculation of the cost of technical connection to the gas network,

- issuance of specifications,

– fulfillment of technical conditions and execution of an act on the readiness of house networks for gas connection,

- the actual connection of the networks of the house to the gas distribution pipe with the preparation of the relevant act.

The rule is canceled that it is possible to connect housing to the gas network without prior issuance of technical conditions and immediately conclude a connection agreement if the gas consumption does not exceed 300 cubic meters. m per hour.

4. The period of validity of the technical conditions for connecting the house to the gas network issued to the applicant has been significantly reduced.

Now it will be 70 working days.

5.The terms for sending the applicant a draft agreement for connecting the house to the gas network are reduced:

- up to 5 working days from the date of receipt of the application - if the gas pipeline passes within the boundaries of the site where the house is located; - up to 30 working days - with consumers of categories 2 and 3, and up to 15 working days - in all other cases.

6. The maximum terms for connecting a house to gas have been specified:

- for category 1 consumers - from 9 months to 1 year, for category 2 - from 1.5 to 3 years, for category 3 - from 2 to 4 years, depending on individual conditions.

7. Reduced terms for paying for gas connection:

- 50% - within 11 working days from the date of conclusion of the contract, the remaining 50% - 11 working days from the date of signing the act of connection.

Haven't gasified your home yet? Getting ready for the new rules!

Stages of documentation

After drawing up the offer, the gas supply organization registers it with the date of receipt. This mark will be the starting point for the start of document verification.

Registration of gas documents: procedure for concluding a contract for gasification

In total, two copies are left, one of which is for the applicant, the second for gas workers.

From the moment of registration of the contract for the gas supply of a private house, the consideration period should be no more than 1 month. Consideration involves checking the completeness of all documents, the reliability of the data and considering the technical feasibility of connecting gas.

If any document is found to be missing, it will be required to be conveyed. The gas organization will report the missing documents by telephony or by e-mail.

After a month or earlier, the gas supply organization must inform the future subscriber about the results of the check. The applicant can also call himself and find out the current status of the verification status.

If no problems arise, the gas supply offer receives the status Approved. Then an agreement is signed for the gas supply of an apartment (private house).Registration of gas documents: procedure for concluding a contract for gasification

The period for which the document is signed is not limited, unless other conditions are provided. The gas supply agreement with an individual or legal entity is drawn up in 2 copies. The first copy goes to the gas service, the second is given to the subscriber by signature. It is also possible to send the finished document to the post office. A prerequisite here is a notification of receipt.

In the case of delays on the part of the gas workers or an unreasonable refusal, the applicant reserves the right to go to court. Also, the failed subscriber may demand the payment of moral and material costs and force, through the court, the gas supply organization to sign the contract.

Obtaining specifications

Registration of gas documents: procedure for concluding a contract for gasificationCadastral plan of the land plot. (Click to enlarge)

Without appropriate technical conditions, it will be impossible to obtain a permit for gasification. To obtain technical specifications, the following must be provided:

  1. In addition to a passport and an identification code, papers are needed confirming the rights to the plot and the house.
  2. Attached is a topographic survey of the site and a cadastral plan, which can be obtained from the chief architect.
  3. You need the original technical passport of housing construction.
  4. The application indicates the heated area, gas consumption, documents for the equipment and the place of its installation.
  5. A chimney survey report and a building permit will be required if the house is unfinished.
  6. The time for studying documents and issuing a permit is 10 days.

In case of a positive decision, it is necessary to find a design organization in order to prepare documentation for the installation and installation. She must have the appropriate licenses and certificates that allow her to engage in this activity.

An offer to conclude a contract

An offer is a proposal to conclude a deal with a gas supply organization, describing the key terms of a future contract. A gas connection agreement is a document containing the basic requirements for the rights and obligations on the part of the applicant and the gas service, as well as the nuances regarding the timing of payment, submission of testimony, details of the payment organization, the availability of benefits and responsibilities of the parties, the term for concluding the agreement, etc. .

Registration of gas documents: procedure for concluding a contract for gasification

The contract is necessary to regulate the relationship between the applicant and gas suppliers. If the future subscriber does not have time to deal with the contract, he can delegate his rights to a third party (agent). Then the agency contract for gas supply will be concluded and signed.

When changing the gas company serving a certain area, the gas company can use the so-called public gas supply contract with the population. This document comes into effect from the moment of publication in the media.

In addition to the supply contract, a gas transportation contract can also be concluded separately. Its difference is that it cannot be concluded publicly.

The contract for the supply of gas to meet the domestic needs of citizens is concluded at the branch of the gas service related to your area. Service specialists can connect the gas in advance (before the conclusion of the contract).True, Article 540 (paragraph 1) of the Civil Code of the Russian Federation says that the contract comes into force from the first day of launching gas into a house or apartment. Those. in fact, the signing of the document can be issued retroactively.

Decree No549 issued by the Government of the Russian Federation on July 21, 2008, which stipulates the procedure for gas supply, significantly expanded the rights of users. And now the gas services recommend citizens to consider the written signing of the contract as a priority in order to avoid legal delays.